Marc - Consultant PRIMAVERA
Ref : 190228B002-
78310 MAUREPAS
-
Consultant, Ingénieur de production (64 ans)
-
Freelance
December 2017 – September 2018 TECHNIP / FMC Paris & Arras
PLANNING & Project Strategy Manager, Time scheduling & planning methodology for the Pharmaceutical EPC Project 2020 in Arras, LFB laboratory
July 2017 - December 2017 WESTINGHOUSE Golfech
PLANNING & Project Strategy Manager, Time scheduling & planning methodology for Nuclear Diesel Generator installation, Post Fukushima
September 2016 - June 2017 ENGIE Axima Switzerland
PLANNING & Project Strategy Manager, Time scheduling & planning methodology for HVAC installation on Pharmaceutical Site construction
April 2015 - August 2016 General Electric Paris
PLANNING & Project Strategy Manager, Time scheduling & planning methodology for Steam Power Plant in Mexico
June 2013 - Mars 2015 Actemuim (VINCI Group) Paris
PLANNING & Project Strategy Manager, Time scheduling & planning methodology for OIl & Gas - Control & Protection Systems Floating Product Units
2007 - Mai 2013 Actemuim (VINCI Group) Paris
PLANNING & Project Strategy Manager. Responsible of the establishment of Time scheduling & planning methodology for the Hydro Power Plants
2005 - 2006 ALSTOM Thermal Power Nuclear
PROJECT PLANNER Senior Manager. Responsible for Time scheduling and monitoring to achieve Turbine-Condenser-Generator Group for Nuclear Plants
2000 - 2005 ALSTOM Power Plant
PROJECT PLANNER Senior Manager. Responsible for Time scheduling and monitoring to achieve Thermal Energy Plants
1993 - 2000 ALSTOM Thermal Power Steam Paris
PROJECT PLANNER. Responsible for Time scheduling and monitoring of outsourcing to achieve Boilers for Thermal Energy Plants and Incineration plants with energy recovery household waste.
1990 - 1992 ALSTOM Thermal Power Steam
DESIGNER. General installation responsible for the study of High pressure pipe systems and instrumentation for power plants boilers.
1985 - 1989 E.C.E (L’Equipement et la Construction Electrique) Paris
DESIGNER. Study and integrated design lighting decks control and navigation systems
1981 - 1984 AXETUDE (Assistance technique) Paris
DESIGNER. Study and design of tools for the automotive and aircraft construction. Study materials for Aerospace
1980 STEIN INDUSTRIE Vélizy (Moved to ALSTOM Thermal Power)
DESIGNER. General installation studies for boilers of power plants..
AREAS OF EXPERTISE
Implementations
Project and Contract Management
Establishment and Management of Site Construction Time Schedule of the new Safety Diesel Generator Post Fukushima on Golfech Nuclear Plant in S-W of France
Establishment and Management of Site Construction Time Schedule of the HVAC network in a Pharmaceutical Plant in Switzerland.
Establishment and Management of Realization, Strategic and Contractual Time Schedules of following EPC projects:
- Power plants "Turnkey" in Mexico, Thailand, Chile, Dubai, China and Uganda
- Incineration plants with energy recovery household waste in France and China
- Turbine-Condenser-Generator Group for Nuclear power plants in China and Sweden
- Control & Protection Systems for Oil & Gas - Floating Product Unit in Congo
Implementation of planning and optimization of associated tools, PRIMAVERA MICROSOFT PROJECT & EXCEL:
- Organization of projects throughout the OBS, WBS and RBS Structures including Standardization of the Codification of the overall planned activities
- Consolidation of Time schedules of ALSTOM Units in France and abroad (Including Site areas) to the Lead Time schedules of Projects
- Optimization of Management Tools for physical progress, analysis of variance and reporting,
Establishment of Excel Monitoring tools filled automatically by the Time schedule software
Study of (3D) CAD general installation of high-pressure piping system for thermal power plant boilers including Piping Stress analysis.
Study in (2D) CAD installation & manufacturing files for embedded systems for aerospace industry and tooling for the aerospace and automotive industries
Great involvement in Team building with permanent collaboration with Project Director, Project Cost control manager, Project Contract manager, Project Risk-Opportunities Manager and Doc Control Manager
Implementation of the Earned Value Management process
Establishment of the necessary databases to validate the reference Time Schedule
- Assimilation of the contract
- Critical path analysis
- Client Interfaces COMPANY and COMPANY-Partners overall agreement of objectives
- Commitment on Contractual milestones
- Risk analysis
Organizing and conducting permanent Time schedule management meetings with responsible of main phases of EPC Projects as Design office, Sourcing Department, Workshops, Logistic Department, Erection and Commissioning Team Management.
Conducting meetings and drafting Minutes of meeting
Publicly present the situation of project deadlines to Project reviews
Frequent overseas travel for coordination meetings with Customers
Frequent overseas travel for coordination meetings with the various Production units, Subcontractors and Sites.
Coordination of a team up to 10 people
Supervision of outsourced studies, manufacturing and final assembly in France and abroad
Time scheduling and following of Workshop manufacturing
Design
Office automation / Language
Establishment of Excel user-friendly monitoring tools available to different stakeholders of the project and filled automatically by the planning software and used for :
- Monitoring the project
- Conducting Planning Meetings
- Drafting minutes of meetings
- Filling Internal and Contractual Reports
Greater involvement on the visual quality of the information published as Time Schedules, Tables,
S-Curves, Graphs.
Modeling in 2D and 3D files following the CAD studies
Primavera P6, Microsoft Project
Word, Excel and Powerpoint
CAD (Autocad) and (Intergraph)
English - Professional Level
Spanish - School level
EDUCATION / TRAINING
1978 Bachelor TECHNICIAN
Section F1
Rambouillet (78) High School
1986 D.A.O. (CAD - 2D)
(Computer Aided Drafting for Design)) Software AUTOCAD
1990 C.A.O. (CAD - 3D)
(Computer Aided Drafting for Conception) Software INTERGRAPH
1993 Project Management Software PSN7
Software PRIMAVERA Suretrack
1999 Project Management Software PRIMAVERA P3
2000 Project Management Software PRIMAVERA P6